Completed Work

Gujarat

One of our star projects is the construction of Asia’s Second Largest Canal Syphon. It has more than 500 km of Open canal network in Gujarat region including its Hydraulic Structures.

We have Developed cultivable command area of more than 2,50,000 Ha in Gujarat benefiting hundreds of farmers.

Project Details
Dhangadhra Branch Canal Construction Canal, Earthwork, Lining, Structure and Service Road for distributories and Minor's for the command area under Dhangadhra Branch Canal ch. 98. 267 to 124. 983
IR - 10 Construction of Kachchh Branch Canal Reach ch. 276.857 km. 284.486 km. (Earth Work, Lining Structurs , Service Road , Gate Work, Control cabin and Operation,Maintenance for five Years (IR - 10)
Long Canal Syphon Construction long Canal Syphon between Ch. 215.272 Km to 217.217 Km. and C.R. At Ch. 215.235 Km.of Kachchh branch canal (Earth work, C.C. Lining, Structures, gates & Stop logs, services road conrol cabin and O & M work for 5 Years
IR_11-12 Construction of branch canal reach Ch. 284.486 to 296.501 KM of Kachchh branch Canal.(IR_11-12)
Slice - II Construction Distributories & Minor work for the command area under vallabhipur branch canal for mithapur distry (D-10), Rolol Distry (D - 11), Hadala Distry (D- 14 ), Rayka Distry (LD - 1B) (Slice - II)
PACKAGE-I (VBC) Consructing Under Ground Pipe Line (UGPL) of 20 minors of Balol Disty (D-12),4 minors of Anandpur Disty (SD-12),2 minors of Panshina Disty (D-13),Chharad minor of Kalam Disty (D-2),3 minors of Derwala disty (D-3), 2 minors of Gadthal Disty (D4),2 minors Kaliveji Disty (D-9),2 minors of Mithapur Disty (D-10) and Gedi minor of Ralol Disty (D-11)) of Vallabhipur Branch Canal with Operation & Maintanance of 5 years(PACKAGE-I) (VBC)
PACKAGE-II (VBC) Constructing Under Ground Pipe Line (UGPL) of 5 Minors of Hadala Disty (D-14), Bajarda Disty (D-15)from ch 7.20 km to 9.644 km and it’s 3 Minors, 15 Minors of Rayaka Disty (LD-1B), Dhandhuka Direct Minor (LD-2B),16 minors of Kamatalav Disty (LD-4B) and 7 minors of Ambali sub Disty (LD-4B-1) of Vallabhipur Branch Canal with Operation & Maintanance of 5 years (PACKAGE-II) (VBC)
Package- I (KBC) Construction of CAD (Distributary including its Minors (UGPL) and Sub Mionors (UGPL) of various Distributary offtaking from Kachchh Branch Canal between Ch. 113.067 Km to 136.727 Km including operation & Maintenance work for 5 years (Package- I) (KBC)
Package- II (KBC) Construction of CAD (Distributary including its Minors (UGPL) and Sub Mionors (UGPL) of various Distributary offtaking from Kachchh Branch Canal between Ch. 139.127 Km to 163.744 Km including operation & Maintenance work for 5 years (Package-II) (KBC)
Package- III (KBC) Construction of CAD (Distributary including its Minors (UGPL) and Sub Mionors (UGPL) of various Distributary offtaking from Kachchh Branch Canal between Ch. 169.958 Km to 178.400 Km including operation & Maintenance work for 5 years (Package- III) (KBC)
Package- IV (KBC) Constructing Distributory Canals including its Minors ( UGPL ),Sub Minors ( UGPL ) off taking from Gagodhar Sub Branch Canal except Gagodhar Tail Distributory including O & M for Five years.(Package-IV) (KBC)
Package- V (KBC) construction of cad(distributory including its minors (ugpl) and sub minors(ugpl) of gagodhar tail distributory offtaking from 57869 m of gagodhar sub branch canal incliding o & m for five years.(Package-V) (KBC)
PACKAGE-2 Constructing Under ground Pipeline (UGPL) of sangasar sub distributary (S.D-1) offtaking from habatpur distributary (LD-10-B) at ch.3.676 km of vallabhipur Branch canal Including Operation, Maintenance and Security for five Years. (PACKAGE-2)
Slice-III Constructing Under Ground Pipe Line (UGPL) of 07 Minors of Mithapar Distributory (SD-1), 01 Br. Minor of Rajgadh Minor (SD-2), 01 Br. Minor of Bhadbhid Minor (SD-3), 04 Minors of Mevasa Distributory (SD-4) and 02 Br. Minors of Sanes Minor (SD-5) of Vallabhipur Branch Canal including Operation Maintenance & Security for Five Years (Slice-III)
Karjan Supplying, Installing and testing of UGPLsystem of Sub Minor for Irrigation through kundies in Chak area for SSP Command of various Sub Minors including maintenance for 5 years under Phase-1 of Executive Engineer, N.P. Canal Dn. No.5, Karjan (Package – 5)
Slice-I Constructing Under Ground Pipe Line (UGPL) Of 13 Minors Of Pipli Distributory(Ld-3B), 3 Minors Of Loliya Sub- Distributory(Ld-3B1), 7 Minors Of Kadipur Distributory (Ld-5B), 10 Minors Of Gorasu Distributory (Ld-6B) And 38 Minors Of Bavaliyari Distributory (Ld-7B) Of Vallabhipur Branch Canal Including Operation Maintenance & Security For Five Years. (Slice-I)
Kalol (PMS) (Package - 3) Supplying, Installing & Testing of UGPL system of Sub Minor for Irrigation through Kundies in Chak area for SSP Command of various sub minors under Phase-1 under Jurisdiction of Executive Engineer N P Canal Division No.17, Kalol (PMS) (Package - 3)
Dabhoi (Package-10) Supplying, Installing & testing of UGPL system of sub minor for Irrigation through kundies in Chak area for SSP Command of various Sub Minors under jurisdiction of Executive Engineer, N P Canal Dn. No. 4A, Dabhoi with five years maintenance (Package-10)
Wandhiya Sub Branch Canal Construction Of Cad [Distributories/ Direct Minors Including Its Minors (Ugpl) And Sub Minors (Ugpl)] Offtaking From Wandhiya Sub Branch Canal Including O & M For Five Years.
Package-DIR- II Constructing Dudhai Sub-Branch canal reach from 11.430 to 23.025 km [Earth work, C.C. Lining, Structures, service Road Gate work, Control Cabins and its operation & Maintenance work for 5 years] (Package-DIR- II )
UGPL (Package CAD-DSBC- 01) Construction of CAD (Distributary (UGPL) including its Minors (UGPL) and Sub Minors (UGPL)) of various Distributaries off taking from Dudhai Sub Branch Canal between Ch.00.000 Km to 12.466 Km (HR-1to HR-5) including operation & Maintenance work for 5 years.(Package CAD-DSBC- 01)
UGPL (Package CAD-DSBC- 02) Construction of CAD (Distributary (UGPL) including its Minors (UGPL) and Sub Minors (UGPL)) of various Distributaries off taking from Dudhai Sub Branch Canal between CH.12.466 Km to 22.756 Km(HR-6 to HR-10) including Operation & Maintenance work for 5 years.(Package CAD-DSBC-02)
Package –UG-II Supplying, Laying, Testing & commissioning of UGPL system of Sub Minor for Irrigation through kundies in Chak area in SSP Command of various Sub minors under the jurisdiction of Executive Engineer, S.B.C. Dn. No. 5/2, Dhrangadhra of Dhrangadhra branch canal with Five(5) years defect liability period. (Package –UG-II)
Package-UG-V Supplying, Laying, Testing & commissioning of UGPL system of Sub Minor for Irrigation through kundies in Chak area in SSP Command of various Sub minors under the jurisdiction of Executive Engineer, S.B.C. Dn. No. 4/1, Limbdi of Limbdi Sub Branch canal with Five(5) years defect liability period(Package-UG-V)
Package –UG-VI Supplying,Laying, Testing & commissioning of UGPL system of Sub Minor for Irrigation through kundies in Chak area in SSP Command of various Sub minors under the jurisdiction of Executive Engineer, S.B.C. Dn. No. 4/2, Limbdi of Limbdi Sub Branch canal with Five(5) years defect liability period.( Package –UG-VI).
Package - 2 Supplying, Laying, Testing & Commissioning of UGPL System of Sub Minor for Irrigation through kundies in Chak area in SSP Command of Various Sub minors under Jurisdiction of N.P. CANAL CIRCLE NO. 4, Vadodara with Five (5) Years Defect Liability period. (Package - 2 )
Paldi station Construction of paldi station which includes RCC works, Arch. Works, PHE works Entry - Exit Structures; Viaduct (Portal & I - Girder ) adjacent to Paldi station (P 171 - P 187) and old High court station (P 239 - P 259) including Track slab, parapet, Hand railing etc. Complete.
Ahmedabad Metro Completion of Balance Works of Rajiv Nagar and Shreyas Metro Stations for Package-1 of North-South Corridor of Ahmedabad Metro Rail Project Phase-I
Banni Regional Water Supply Scheme Design and construction of WTP @ Lakhond HW, RCC U/G Sump, Pump House at various places & Civil Works & Providing, Supplying, Lowering, Laying & Jointing Pipeline & Supply, Installation, Testing & Commissioning of Pumping Machinery with Operation & Maintenance of All type Machineries for 5 Yrs. under Banni Regional Water Supply Scheme Taluka –Bhuj of District Kachchh
Pipe distribution network Providing of Pipe distribution network for irrigation through kundies in command area of Limbdi, Chanashma, Dhandhuka, Mehsana, Harij and Surendranagar for Culturable command area.

Madhya Pradesh

Project Details
Guna Cement Concrete Lining of canal network and repair / restoration of structures of canal and dam etc. of Rampur medium project under Extension, Renovation and Modernisation ERM of Makroda Rampur Medium Proj. Distt. Guna
Tawa Project, Hosangabad Construction Of Cement Concrete Lining, Of Tawa Left Bank Main Canal From R.D.45780M.To 90240M. Of Tawa Project, Hosangabad
Bhiladia Cement Concrete Lining Of Bhiladia(0 Km -21.66 Km ) And Choutlay ( 0Km-19.83 Km) Distributary And Renovation And Strengthening Of 40 Nos Structures For Choutlay Distributary Of Tawa Left Bank Canal Tawa Project.( Bhiladia)
Sohagpur Cement Concrete Lining, Construction Of Structure & Repairing Of Old Structure Of Sankla Disrtributory From Rd 0 M To 23910 M, Machha Distributory From Rd 0 M To 15450M, Structure Of Purena Distry. Of Pipariya Branch Canal And Sukkarwara Distributory From Rd 0 M To 30090 M, Nasirabad Distributory From Rd 0 M To 18660 M Of Bagra Branch Canal Of Tawa Project On Turnkey Basis (Sohagpur)
Harda Construction Of Cement Concrete Lining In Machakdistributary, Khirkiya Canal, Rewapur Distributary And Sontalai Distributary And Repair Work Of 31 Nos Damaged Structures Of Rewapur Distributary Of Left Bank Main Canal Of Tawa Project, District Harda (M.P.)
Barkheda Construction Of Right Side Flank Ogee Spillway, Of & Nof Section, Sluice, Earthen Dam, Bridge & Its Allied Works And Supply And Erection Of Radial Gates & Gentry Crane Etc. For Berkheda Medium Irrigation Project, Mp (Barkheda)
Parbati Construction Of Composite Gravity Dam On River Parbati Of Least Gross Capacity Of 172.54 Mcm On Turnkey Basis (Parbati)
Sitanagar Project Construction Of Composite Gravity Dam with Pressurised Irrigation network system under Sitanagar Project on EPC basis in the Dist.:- Damoh (MP)
Madia Construction Of Composite Gravity Dam On River Bina Of Gross Capacity Of 270.10 Mcm On Turnkey Basis (Madia)
Rajond Multi- Village Scheme Engineering, Procurement, Construction, Testing, Commissioning, Trial Run and Operation & Maintenance of Various Components of Rajond Multi- Village Scheme, District Dhar in Single Package on ‘Turn-Key Job Basis’ including Trial Run and Operation & Maintenance of the Entire Scheme for 10 Years
Seep Kolar Link Project Remedial Measures & Restoration Work between Seep Weir to Kaldev Weir & Kaldev Weir to Kolar Reservoir in Seep Kolar Link Project under S.D.M.F. Grant (Block : Ichhawar, District: Sehore)

Maharashtra

Project Details
GURUKUNJ (Dist. Amravati) Construction of Pipe Line Distribution Network for command area of 7109Ha. including detailed designing with Construction as per approved design, formation of WUA, handing over the command area to WUA, maintaining the whole system for a period of 60 months after completion, out of which first 3 years irrigation with WUA and next 2 years handing over the area to WUA and irrigation with them for GURUKUNJ LIS Tq. Tiwasa Dist. Amravati.
Akot Lift Irrigation Scheme Construction of Akot Lift Irrigation Scheme by Pipe Distribution Network and a 260 KW grid connected Solar Power Plant on Design, Engineering, Procurement & Construction (EPC) basis along with Comprehensive Maintenance and Operation for 05 (Five) Years after successfully commissioning of scheme and plant.
Marhegaon (Bhandara) Design, Construction and Commissioning of Marhegaon and its tail branch Canal with their PDN and CAD works for Irrigation of 4034 Ha CCA including Operation and Maintenance of PDN & CAD for 05 (Five) Years for VIDC at Bhandara District of Maharashtra
Gosi (Bk) Execution of Gosi (Bk) Lift Irrigation Scheme

Rajasthan

Project Details
Package GL-1 Development of pressure irrigation system on turnkey basis in command area of Bhanipura Disty, Bijar minor, Chillan Minor, Ramsar minor, Jaimalsar Disty, Jageriwala disty, Kanasar Disty, Shobhasar Minor of Pannalal Barupal Lift Canal (Package GL-1)
Package GL-2 Development of pressure irrigation system on turnkey basis in command area of Lakhasar Disty., Randhisar Minor, Randhisar Sub Minor, Surjera Disty., Agenau Minor, Bannewala Minor of Pannalal Barupal Lift Canal.(Package GL-2)
Package KL-1 Development of pressure irrigation system on turnkey basis in command area of Kumhar Disty. Arjun Minor, Bhuaji Minor, Suthar Minor, Kumhar Minor, Nagrasar Disty, Panchvati Minor, Nagrasar Minor, Khidrat Disty, Kolasar Minor & Kolasar Sub-Minor of Dr. Karni Singh Lift Canal.(Package KL-1)

Odisha

Project Details
Harabhangi Irrigation Project Extension of Harabhangi Irrigation Project 3763Ha GCA(2800Ha CCA) in Seragada & Aska Block of Ganjam District (Extension through U.G.P.L. (Gravity flow) Under Nabakrushan Choudhury Secha Unnayan Yojana ,ERM)

Delivering Results with Solid Dependability